A typical residential tower in Dubai wraps in ~2–4 years, while a large master-planned community needs ~4–5+ years, usually in phases.
What that actually means for you
If you’re budgeting, negotiating SPAs, or aligning off-plan milestones to cash flow, timing isn’t a footnote—it’s your risk model. Towers tend to be more predictable. Communities? More moving parts: roads, utilities, clusters, amenities, and staggered handovers.
How I see it play out on real deals
I’ve watched 60+ storey towers hit practical completion around the 3–4 year mark, with smaller mid-rise buildings sometimes delivering in 18–36 months when funding and approvals move fast. Master communities stretch longer—4–5 years or more—because infrastructure and amenity sequencing slows the final “complete community” picture, even if early phases hand over sooner.
Timelines you can actually use
Towers (high-rise and mid-rise)
- Overall completion: ~2–4 years (most 60+ storey towers: 3–4 years).
- Smaller/mid-rise: 18–36 months in efficient conditions.
Structural works (the critical path):
- Foundation (excavation, piling, raft): ~6–9 months.
- Superstructure (columns, slabs, floors): ~12–18 months; efficient cycles can hit 5–8 days per floor.
- Total structural window: roughly 12–24 months before cladding/MEP/finishes ramp.
Large communities (master-planned)
- Overall completion: ~4–5+ years, typically phased (infrastructure → residential clusters → amenities).
What moves the timeline (and your contract risk)
Honestly, schedules slip for boring reasons that cost real money. Here’s what I pressure-test in documents and developer representations:
- Scale & complexity: height, basement count, unique design features.
- Funding & contractor performance: payment flows, subcontractor depth.
- Regulatory & approvals: sequencing of permits, inspections, utilities.
- Market & logistics: material availability, supply chain bottlenecks, weather.
Bottom line
You can plan a tower on a 2–4 year arc and a large community on 4–5+ years—then add buffer for the real world. But here’s the thing: when you build your deals around realistic windows and phase-based triggers, you protect your cash flow and your sleep.